With MS PROJECT 2000 ; A strange behaviour when a couple of projects are linked in a master project.


What exactly I did.


- I planned separately 3 projects : P1, P2, P3.

- I insserted the 3 projects in a central one : PMASTER.

- I defined a resource pool in PMASTER and allowed P1, P2 and P3 to share resources.

- The efforts (Work) et Duration values unit is «day».



First result (seems to be correct).



- In a first check ; the merge worked but one task of P1 is marked «critical» in PMASTER and not in P1 plan.



Second result (Strange!).



- 24 hours after, I reopen the 4 files. Surprise ! Durations have been automatically recalculated and replaced by other numbers with decimal digits ???



- Also, anytime I open the PMASTER project, a second file (Project1) is created. The content of Project1 is very similar to the content of PMASTER ???



- A look to the «resource usage» table does also show me (for a week, 5 days planning) the values 1.14d 1.14d 1.14d 1.14d 1.14d instead of 1d 1d 1d 1d 1d ???



- The critical task is still «critical» in PMASTER and not in P1. I do not understand why ???



Thanks in advance for your help.